PC Construction's contract works included the excavation, placement of foundation and backfill, supply and construction of gabion walls which are being used to retain the corner of a new housing development. There was also an existing drainage channel that had to be kept clear of fill material.
- Face Area: 180m³
- Height: 7m
- Construction time: 5 days